Late Payments in Construction: What UK Tradespeople Can Do to Get Paid
Learn how UK tradespeople can tackle late construction payments, chase overdue invoices, understand legal rights and protect their business cash flow.
You finished the job weeks ago, the invoice went out on time, and the customer has stopped replying. Meanwhile, your supplier wants paying and the van still needs fuel. Late payment is one of the most common pressures on small construction firms and self-employed trades in the UK, and it rarely resolves itself. The good news is that you have more options than many people realise, and the earlier you use them, the better your chances of getting paid without a long dispute.
Start by checking what was actually agreed
Before chasing anyone, work out exactly when payment was due. That sounds obvious, but a surprising number of disputes turn on it. Look at your quote, contract, purchase order or any email exchange that set out the terms. Is the due date counted from the invoice date, from the date the work was approved, or from the end of a monthly cycle? Was there a staged payment schedule, a deposit or a retention that affects the amount?
If the work was done for a main contractor or business, a formal contract may set out payment notices, valuation dates and a final date for payment. If you worked for a homeowner on a verbal agreement, you will be relying on whatever you can show in writing, along with the general rules on contracts. In either case, gather your paperwork in one place: the quote, any variation instructions, photographs, delivery notes and the invoice itself. You will need them whether the next step is a polite reminder or a court claim.
Chasing the money without souring the relationship
Many late payments are down to disorganisation rather than bad faith. An invoice sent to the wrong person, a purchase order missing from the paperwork or a payment run that was missed can all hold things up. A short, friendly message the day after the due date is often enough to shift it. Confirm the invoice amount, the due date and how to pay, and ask when you can expect settlement.
If nothing happens, follow up in writing within a few days. Email is useful because it leaves a record, but a phone call afterwards can sometimes uncover the real problem, such as a query on part of the invoice. If there is a genuine dispute about one item, ask for it to be put in writing and ask for the undisputed part to be paid in the meantime. That keeps the conversation moving and narrows the issue.
Keep a log of every contact: dates, who you spoke to and what was said. If the matter escalates, a clear record of reasonable attempts to resolve it makes your position much stronger.
Charging interest and compensation on business invoices
If your customer is a business, you have a statutory right to claim interest and fixed compensation on overdue invoices under the Late Payment of Commercial Debts (Interest) Act 1998. This applies where the contract does not already provide a substantial remedy for late payment. The Act sets interest at a rate linked to the Bank of England base rate, plus a fixed sum depending on the size of the debt. Because the base rate changes, check the current figures on GOV.UK before putting any numbers on an invoice.
The Act does not generally help with debts owed by private individuals, so homeowners fall outside it. It is also worth mentioning that many tradespeople never claim this interest, partly because they worry about damaging the relationship. Stating your right to it in a firm but courteous reminder often prompts a quicker response. Including late payment terms on your invoices from the start makes that conversation easier.
The formal letter before court
When reminders have failed, send a formal letter setting out what is owed, how the amount is calculated, what the payment terms were, and a date by which payment must be made. Fourteen days is a common period, though the circumstances may justify longer or shorter. State clearly that you intend to start court proceedings if payment is not received. This is often called a letter before action.
Sending one is more than a pressure tactic. Courts expect parties to try to resolve a dispute before issuing a claim, and a debtor who ignores a clear letter will find it harder to explain themselves later. If the debtor is an individual, a specific pre-action protocol for debt claims may apply, requiring certain information to be included, so check the current requirements or take advice if you are unsure.
Using the Construction Act where it applies
For commercial construction work, the Housing Grants, Construction and Regeneration Act 1996 (the Construction Act) gives subcontractors and other contractors some powerful tools. It generally does not apply where the contract is with a homeowner for work on their own home, but it often does apply to work for builders, developers and other businesses.
Under the Act, the paying party must usually issue a payment notice and, if it wants to pay less than you applied for, a pay less notice within the required timescales. If it fails to do so, the sum you applied for may become payable in full. The Act also gives you a right to suspend work for non-payment, provided you have given the required notice of your intention to do so, which is seven days under the statutory rules. Suspension is a serious step and can have consequences if you get the process wrong, so read your contract and take advice before using it.
Adjudication
The Act also gives you the right to refer a payment dispute to adjudication at any time. An adjudicator usually reaches a decision within 28 days of the referral, though this can be extended in some circumstances. The decision is binding in the short term, even if one party later challenges it in court or arbitration. It is quicker and often cheaper than litigation, but it involves preparing a proper case and paying the adjudicator's fees, so it tends to make more sense for larger or more contested sums.
Going to court
If the debt is not paid, a county court claim is the usual route. Claims up to £100,000 can generally be started online through Money Claim Online, and smaller claims, typically those up to £10,000, are normally dealt with on the small claims track, where costs you can recover are limited. You pay a court fee based on the amount claimed, and you may be able to recover it from the debtor if you win.
A judgment does not guarantee payment. If the debtor still does not pay, you may need to take enforcement action, such as instructing bailiffs or seeking an attachment of earnings order, each of which has its own process and cost. It is worth thinking realistically about whether the debtor has the means to pay before spending money on enforcement.
Time limits matter too. For most simple contract debts in England and Wales, you have six years from the date the debt became due to bring a claim, though you will want to act far sooner. Scotland and Northern Ireland have their own procedures and time limits, so check the rules that apply where you are.
When the customer is a company in difficulty
If you are owed money by a limited company that appears to be struggling, speed matters, because you will be an unsecured creditor and may be paid little or nothing if it enters insolvency. A statutory demand is one route available against a company for debts above a minimum threshold, and it can lead to a winding-up petition if ignored. It is a serious step with costs and consequences, so it is usually worth speaking to a solicitor or a debt recovery specialist before using it, especially if the debt is disputed.
Preventing the next late payment
Most late payment problems are easier to prevent than to fix. Agree payment terms in writing before starting, and make sure variations are confirmed before you carry them out. Ask for a deposit on larger or materials-heavy jobs, and invoice at agreed stages rather than waiting until the end. Keep invoices clear, with the job address, a reference number, a breakdown of costs and the due date.
Who you work for makes as much difference as any clause in a contract. Asking around about how a contractor or client pays, and building relationships with other trades, gives you early warning of anyone with a poor record. A guide on how Plumbers Find Trusted Tradespeople through referrals is a good place to start if you want to build that kind of network.
It also helps not to depend on a handful of customers. Spreading your work across more clients reduces the damage when one of them pays late. A construction platform for plumbers can be one way to meet contractors and developers outside your usual circle, which gives you more choice about who you work for and on what terms.
Conclusion:-
Pick one overdue invoice, or the next one you send, and check three things: whether the due date is written down, whether your invoice states your right to charge interest on late payment, and whether you have a simple routine for following up at seven and fourteen days. Those small steps are often what separates a quick payment from a long chase. If a sizeable debt is already seriously overdue, a short conversation with a solicitor or your trade body can help you choose the most sensible route before costs start to build.


cnndailyupdates